About the project
One of the UKs leading office fit out Fabric Contractors sought to develop a new show room in the heart of Clerkenwell “Shop Design” were employed to design, develop and complete the task as a Principle Contractor.
With 12 weeks to strip out and present the completed showroom in an occupied building, the programme and planning was crucial.
Combining new plant and equipment for heating and cooling which challenged logistics, requiring a crane lift to an external roof. High end strip lighting including feature lighting integrated with acoustic ceiling rafts. And high end finishes that promotes Kvadrats high level of quality. All delivered in good time for Kvadrat to showcase themselves at Clerkenwell Design week.